Introduction #

When this guide fits: You are scoping new or retrofit HVAC for a high-bay factory (production + warehouse + QC) and need a documented zone load table, ventilation strategy, and system archetype before equipment hits the bid room.

When it is not suitable: Explosion-rated classifications, ISO cleanroom validation, or stamped refrigerant inventories require licensed mechanical engineers and code-specific submittals beyond this field record.

Verified: 2026-05-25 — design basis for the 12,000 m², 12 m clear-height packaging campus referenced in HVAC Load vs Capacity (500 kW coincident peak, later rightsized from 650 kW installed).

Design loop: loads, ventilation, distribution, commissioningLoadsVentilationDistributionCx

Design-day inputs we froze (revision C, 2025-11) #

Input Value Source / note
Floor area (conditioned) 12,000 m² BIM shell v3.2
Clear height 12 m High-bay packaging
Outdoor design 32 °C DB / 24 °C MC WB ASHRAE 0.4% dry + coincident wet
Indoor target (production) 22 °C DB, 50–55% RH QA moisture spec
Shifts 2 × 10 h + 1 h overlap Not 24 h full load
Dock doors 6 × 4 m, scheduled open Infiltration schedule in model

Zone load schedule — basis for coincident 500 kW #

Do not sum the “Peak kW” column for equipment sizing—that was the original 650 kW bid error. Use coincident row at bottom.

Zone Floor m² Sensible peak kW Latent peak kW Hours occupied Non-coincident?
Lines 1–4 (packaging) 6,800 248 42 06:00–22:00 No
Warehouse mezz 2,400 52 8 08:00–18:00 Partial
QC / metrology 900 38 22 07:00–19:00 No
Offices + MCC 1,100 28 6 07:00–18:00 Yes (off-peak)
Dock vestibule 800 18 4 Intermittent Partial
Arithmetic sum of peaks 384 82 466 kW (wrong basis)
Coincident design (Aug 15 h) 412 88 500 kW

Sanity-check zones in the HVAC Capacity Calculator; electrical feeders via Factory Load Calculator.

Post-bid outcome and RH fixes: HVAC Load vs Capacity case.

Ventilation and exhaust — OA that drove latent load #

Source Design flow (m³/s) Tempered? Latent impact
Occupant OA (production) 12.4 Yes Moderate
Dock infiltration (scheduled) 8.2 Yes High humid mornings
Seal-bar exhaust 6.5 Makeup required Dominant latent
General roof exhaust 4.0 Partial Dust control

Decision: Dedicated DOAS unit for OA dehumid (latent wheel), sensible cooling on three staged DX zones—avoid mixing all OA through oversized packaged DX.

Space type Planning ACH (conceptual) Governing driver
Production hall 6–8 Heat + dust dilution
QC lab 12+ changes Spec + pressurization
Warehouse mezz 4 Inventory heat only

Always verify against local code and occupational exposure limits—not this table alone.

Air distribution choices #

Zone Issue Selected approach
Production Stratification at 12 m High-throw diffusers + destrat fans at 8 m
Warehouse Low internal gain Smaller sensible coil, night setback
QC Tight RH Independent zone, DOAS dry OA
Offices Misleading if tied to bay Separate thermostat, not bay SP

Filter train: MERV 8 pre + MERV 13 main on production AHUs; monitor ΔP—fouling mimicked “undersized HVAC” in year-one ops.

System archetype comparison (why we rejected single RTUs) #

Option First cost index Humidity control Part-load Verdict
2 × large packaged DX 1.0 Poor latent Short cycle Rejected (became 650 kW problem)
Central chiller + AHUs 1.35 Good Excellent Deferred (capex gate)
DOAS + staged DX 1.18 Good Good Selected in retrofit

Electrical and energy coordination #

Load item Connected kW (HVAC stack) Notes
Compressors (staged) 380 Nameplate sum
Condenser fans + VFD 48 Include on one-line
DOAS wheel + fans 62 Do not omit on factory sheet
Pumps (future CHW) 0 Spare breaker only

Coarse cost swing: Energy Estimator after demand kW moved in the site energy audit.

Browse HVAC calculator hub.

Instrumentation specified at turnover #

Minimum BMS points so rightsizing debates end with data:

  • Filter ΔP each stage
  • OA damper position feedback
  • Zone RH at coil leaving air path
  • Fan kW (not % speed alone)
  • CHW ΔT if hydronics added later

Commissioning: 15-minute trends for two production weeks, not TAB design-day only.

Next steps you should take #

  1. Publish a one-page zone schedule with coincident peak highlighted—not column sums.
  2. Model humid-hour latent separately from afternoon sensible peak.
  3. Match system type to OA + exhaust chemistry before requesting bids.
  4. Specify trend points in the controls spec—not a post-occupancy argument.
  5. Cross-check tonnage in the HVAC Capacity Calculator (page 2026-05-25).
Do industrial bays always need more tonnage than offices?

Not automatically—high internal gain can be offset by stratification, exhaust, and shift schedules. Model each zone; avoid copying office W/m².

When is DOAS worth the complexity?

When tempered OA + process exhaust drives latent load that packaged DX cannot handle without short cycling—this site is the reference case.

What commissioning mistake cost us RH control?

Treating **design OA as installed minimum without proving damper position and filter DP under full exhaust.

Should electrical design use compressor kW only?

No—include condenser fans, DOAS, pumps, and auxiliaries on the factory load sheet.

How do zone peaks relate to equipment nominal?

Size on the coincident envelope—see the load vs capacity case for what happens when you sum zone maxima.