Connected 682 kW vs Demand 491 kW: Sizing Impact on Transformer & Main
Introduction #
When this guide fits: A stakeholder says “we have 682 kW, size for that” while the utility bill shows a lower 15-minute peak—and you need one slide that explains which number feeds transformers, mains, and tariffs.
When it is not suitable: Branch circuit ampacity for a single motor feeder—use NEC branch rules, not facility demand concepts.
Verified: 2026-05-25 — packaging campus figures used across load mistakes, diversity factor, and distribution one-line.
Definitions — one facility, two numbers #
| Term | Meaning | This plant |
|---|---|---|
| Connected load | Sum of equipment nameplate kW (everything on at 100%) | 682 kW |
| Demand load | Utility billing peak (or metered coincident max) | 491 kW |
| Gap | Connected − Demand | 191 kW (28%) |
Connected is the inventory ceiling. Demand is what actually sets transformer % load, main breaker heat, and demand charges.
Inventory table — where 682 kW came from #
| Equipment | Qty | kW each | Connected kW |
|---|---|---|---|
| Form/fill lines | 4 | 85 | 340 |
| Seal welders | 6 | 8 | 48 |
| Compressors | 2 | 45 | 90 |
| Chillers (nameplate) | 2 | 55 | 110 |
| Lighting + controls | — | — | 52 |
| Offices + misc | — | — | 42 |
| Total connected | 682 |
Demand load is not this table times one magic factor—it is the metered peak below.
Demand proof — where 491 kW came from #
| Source | Peak kW | Window |
|---|---|---|
| Utility bill (billed demand) | 491 | 15-min, Mar 2026 |
| PQ analyzer MSB | 488 | Same week |
| Intern spreadsheet (wrong) | 375 | 682 × 0.55 ❌ |
Coincident factor: 682 ÷ 491 = 1.39 — see diversity factor guide.
Sizing comparison — wrong vs right number #
| Equipment | Sized on 682 kW (wrong) | Sized on 491 kW @ PF 0.82 (right) |
|---|---|---|
| Apparent power | 682 kVA (PF=1 error) | 599 kVA |
| Transformer ordered | 750 kVA (overspend story) | 750 kVA OK with margin |
| Main breaker guess | 900 A | 800 A |
| Annual extra loss (transformer idle) | ~$1.8k | Baseline |
PF-aware kVA: kW to kVA Calculator. Full walkthrough: Factory Load Calculator.
Cost of picking connected (field dollars) #
| Outcome | Approx. impact |
|---|---|
| Oversized transformer capital | $8,200 |
| PF=1 on 491 kW → 500 kVA underrun | $15,400 downtime (mistakes) |
| Fantasy 375 kW demand | Nuisance trips + scrap |
Who uses which number #
| Decision | Use connected | Use demand |
|---|---|---|
| Transformer / main kVA | ✓ | |
| Utility demand charge | ✓ | |
| Branch breaker to one motor | ✓ (nameplate × rules) | |
| “How big is my building?” story | ✓ | |
| Energy kWh estimating | blend | ✓ for peak kW |
Tariff lines: Energy cost optimization.
Worked conversion — demand to main amps #
kW = 491
PF = 0.82
kVA = 491 ÷ 0.82 = 599
I = 599,000 ÷ (√3 × 480) ≈ 720 A
→ standard main 800 A
Check feeders with Breaker Size Calculator.
Distribution context: Electrical distribution design. Browse Power calculator hub.
Related articles #
- How to Calculate Factory Load
- Factory Load Calculation Examples
- How Factory Load Affects Energy Cost
- Safety Margin in Factory Load
Next steps you should take #
- Build the connected inventory table in kW.
- Pull utility 15-min peak for the same month.
- Size transformers/mains on demand kVA, not connected.
- File both numbers in the project memo—prevent “682 kW” shorthand in bids.
- Request GSC re-index after edits (2026-05-25).
Can I add 20% margin to connected load instead of using demand?
No—that double-counts conservatism. Apply margin to metered demand kVA, documented in the safety margin guide.
Why is demand lower than connected if everything runs?
Machines rarely hit nameplate simultaneously; some are standby, cycling, or on reduced settings—the **191 kW gap** is normal here.
Does connected load matter for permits?
Yes—for **service entrance paperwork** and arc-flash inventory—but operating sizing still follows demand for mains.
What if demand exceeds connected?
Investigate **meter CT errors**, **missing nameplates**, or **power factor/reactive** billing registers—not true demand above inventory.
How do I explain this to non-engineers?
Connected is everyone’s max badge added up; demand is what the meter saw on the worst 15 minutes—you bill and size mains on the second.